What Is a Section 408 Permission?

Quick Answer: Section 408 requires permission from the USACE to alter federal civil works projects, protecting public infrastructure from unauthorized changes. The Section 408 Review process analyzes proposed alterations to ensure they do not impair the project’s usefulness.

Reviewed and updated 10/23/2026 by Marc Foster AICP CEP, Principal Environmental Planner

Introduction

Section 408 permission is a critical requirement for engineers, developers, project managers, and anyone involved in projects that may impact U.S. Army Corps of Engineers (USACE) civil works. If you are searching for “what is Section 408” or need to understand permission to alter federal civil works projects, this guide is for you.

Section 408 of the Rivers and Harbors Act requires that anyone seeking to alter, occupy, or use a federal civil works project must first obtain permission from the U.S. Army Corps of Engineers, in order to protect public infrastructure from unauthorized changes. Understanding Section 408 matters because it is a threshold approval for any project that could affect levees, navigation channels, floodwalls, or other federal infrastructure. Failing to secure Section 408 permission can delay or halt your project.


What “civil works” means here for the Army Corps

Corps civil works are the projects the Corps built or operates for navigation, flood risk reduction, hurricane and storm damage reduction, and related purposes. On the northern Gulf that often means:

  • Federal levees and floodwalls
  • Deep-draft or shallow-draft navigation channels
  • Jetties, breakwaters, and coastal structures the Corps owns, maintains or built
  • Pump stations, gated structures, and associated rights-of-way that are part of an authorized project

If your pipeline, outfall, bulkhead, crossing, or fill would sit on, cut through, or change how that federal project performs—including how it functions or the support it provides for navigation or flood-risk purposes—Section 408 is in the conversation. Private levees and local ditches are not automatically subject to Section 408 just because someone called them a “levee.”

Now that we’ve defined civil works, let’s look at how Section 408 permission applies to these projects.

What Is Section 408 Permission?

Section 408 is 33 U.S.C. § 408, codified in the United States Code and governing the USACE permission process. It says you may not build on, alter, or occupy a U.S. Army Corps of Engineers civil works project—levees, federal channels, jetties, hurricane-protection features, and similar—in a way that hurts the project’s usefulness unless USACE approves it through the review process for obtaining permission.

For engineers, developers, project managers, and others planning or executing work that may affect Corps civil works projects, especially on Gulf Coast jobs, that distinction matters because changes to federal flood-control, navigation, and coastal infrastructure can trigger a separate federal approval before work moves forward. This section explains what Section 408 permission is, when it applies, how it differs from Section 404 and Section 10 permits, the kinds of projects that commonly trigger review, and what USACE evaluates during the process.

Next, let’s clarify how Section 408 differs from other common USACE permits.

Separate from Section 404 and Section 10

Authority

Core question

Section 404

Discharge of dredged or fill material into waters of the United States?

Section 10

Work or structures in navigable waters of the United States?

Section 408

Alteration or occupation of a Corps civil works project?

You can need one, two, or all three. Each authority has separate rules, and Section 408 is not answered by the same determination used for Section 404 or Section 10. A bulkhead on a federal channel can be 10 and 408. Fill in a wetland behind a federal levee can be 404 and 408. A JD for wetlands does not answer whether a proposal is eligible for Section 408 permission. See 401 vs 404 and What is a jurisdictional determination?.

Section 208 (areawide water quality management planning under the Clean Water Act) is a different statute. It sometimes appears in older planning documents; it is not a substitute for 408 permission on a Corps levee.

Understanding these distinctions helps you determine which permissions your project may require. Next, let’s explore when Section 408 typically comes into play on Gulf Coast projects.

When Section 408 Shows Up on Gulf Projects

Section 408 permission is commonly triggered in the Mobile, Vicksburg, New Orleans, and Jacksonville Districts by:

  • Utility or road crossings of a federal levee or floodwall
  • Outfalls or docks that encroach on an authorized channel or its real estate interest
  • Shoreline or marsh work that would change a Corps coastal or navigation feature
  • Development that wants to modify drainage through a federal flood-risk project

District-Specific Procedures and Timelines

Real estate instruments, operation and maintenance manuals, and the district’s 408 procedures matter as much as the engineering sketch, and district-specific provisions may also control what can be built on or through the project. The district that owns or operates the civil works project is the one that must be satisfied the alteration is not injurious and is not a showstopper for the authorized purpose, and it may request additional such information needed to make that determination.

Timelines are their own track. The review can require significant agency resources and subject input before approval. Do not assume a nationwide 404 verification pulls 408 along for free.

Now that you know when Section 408 applies, let’s look at what the review process involves.

Legal Basis & Review Process for Section 408

  • Statute: Rivers and Harbors Act Section 408 requires permission to alter federal civil works projects.
  • Purpose: Section 408 protects public infrastructure from unauthorized alterations.
  • Review: The Section 408 Review process analyzes alterations to civil works projects to ensure they do not impair the project’s usefulness.
  • Permitting: Section 408 Review is required before issuing USACE permits for project alterations.
  • Threshold Approval: Successful 408 Review is a threshold approval for project alterations.
  • Policy Update: The USACE issued a policy change for 408 Review in January 2018.
  • Guidance: The USACE conducts 408 Reviews under Engineering Circular 1165-2-216.

What the Review Is Looking For

Review Criteria

At a high level, the Corps, as the reviewing agency, asks whether the proposed alteration is consistent with the authorized purpose of the project and:

  • Impairs the usefulness of the federal project
  • Is injurious to the public interest
  • Meets engineering and safety expectations for that type of works (levee integrity, channel conveyance, structural stability) and can be maintained safely over time

Required Documentation

You will usually need:

  1. Drawings that show the federal feature
  2. Geotechnical or structural detail where the contact is serious
  3. A clear construction sequence
  4. An account that clearly addresses construction sequencing, impacts, and any supporting engineering detail

Exact submittal checklists are district-specific; we do not invent them here.

With an understanding of the review process, let’s clarify what Section 408 does not cover.

What Section 408 Is Not

  • Not state coastal consistency or 401 by itself
  • Not blanket approval to fill wetlands landward of the levee
  • Not something you “add later” after the sheet pile is ordered, since delay or failure to account for Section 408 early can disrupt the project schedule

Next, see how we help clients navigate Section 408 requirements.

How We Use It

We flag Corps civil works early to address Section 408 issues before separate permit requests are submitted, separate the 408 path from 404/10, and put the engineering package in front of the right district. Cypress Environment & Infrastructure works from Biloxi, Mobile, and Pensacola, in the Mobile, Vicksburg, New Orleans, and Jacksonville Districts. Office hours are Monday–Friday, 9 a.m.–5 p.m.

We can support you through the USACE review and help determine what information the district will request. Questions about your project? Contact Cypress Environment & Infrastructure or call 228-596-1580.

See projects. This page is not a 408 application form and not a site opinion.